Budget and Risk Management Summary
2015-16 Initial Budget (A) |
2015-16 Revised Budget (B) |
2015-16 Actuals (C) |
2016-17 Initial Budget (D) |
2015-16 Revised Budget to 2015-16 Actuals Variance (B-C) |
2016-17 Initial Budget to 2015-16 Actuals Variance (D-C) |
|
---|---|---|---|---|---|---|
Budget Administration | 671,644 | 1,167,450 | 1,104,344 | 683,254 | (63,106) | (421,090) |
Enterprise Risk Management | 318,093 | 445,848 | 332,272 | 321,405 | (113,576) | (10,867) |
Budget and Risk Management Total | 989,737 | 1,613,298 | 1,436,616 | 1,004,659 | (176,682) | (431,957) |
*Benefits are budgeted centrally and then allocated throughout the year. The benefit amount reflected in the 16-17 Budget Column is a projected figure.
Budget Administration Budget Detail
Expense Type | Budget Category | 2015-16 Initial Budget (A) |
2015-16 Revised Budget (B) |
2015-16 Actuals (C) |
2016-17 Initial Budget (D) |
2015-16 Revised Budget to 2015-16 Actuals Variance (B-C) |
2016-17 Initial Budget to 2015-16 Actuals Variance (D-C) |
---|---|---|---|---|---|---|---|
Revenues | |||||||
General Fund Allocation | - | - | - | - | - | - | |
Reimbursed Release Time - NR101 | - | - | - | - | - | - | |
Indirect Cost Recovery - Overhead Distribution | - | - | - | - | - | - | |
Total Revenue Allocation | - | - | - | - | - | - | |
Expenditures | |||||||
Salaries | 645,288 | 653,320 | 611,625 | 630,226 | 41,695 | 18,601 | |
Reimbursed Release Time | - | - | - | - | - | - | |
Total Salaries and Reimbursed Release Time | 645,288 | 653,320 | 611,625 | 630,226 | 41,695 | 18,601 | |
Operating Expenses | 26,356 | 223,789 | 202,377 | 53,028 | 21,412 | -149,349 | |
Total Expenditures (not including Benefits) | 671,644 | 877,109 | 814,003 | 683,254 | 63,106 | -130,749 | |
Benefits* | - | 290,342 | 290,342 | 280,078 | - | -10,263 | |
Total Expenditures and Benefits: | 671,644 | 1,167,450 | 1,104,344 | 963,332 | 63,106 | -141,012 | |
Results of Operations | |||||||
Transfers To | - | - | - | - | - | - | |
Transfers From | - | - | - | - | - | - | |
Total Funding Transfers To/(From) | - | - | - | - | - | - | |
Total Expenses and Funding Transfers | 671,644 | 1,167,450 | 1,104,344 | 963,332 | 63,106 | -141,012 |
*Benefits are budgeted centrally and then allocated throughout the year. The benefit amount reflected in the 16-17 Budget Column is a projected figure.
Enterprise Risk Management Budget Detail
Expense Type | Budget Category | 2015-16 Initial Budget (A) |
2015-16 Revised Budget (B) |
2015-16 Actuals (C) |
2016-17 Initial Budget (D) |
2015-16 Revised Budget to 2015-16 Actuals Variance (B-C) |
2016-17 Initial Budget to 2015-16 Actuals Variance (D-C) |
---|---|---|---|---|---|---|---|
Revenues | |||||||
General Fund Allocation | - | - | - | - | - | - | |
Reimbursed Release Time - NR101 | - | - | - | - | - | - | |
Indirect Cost Recovery - Overhead Distribution | - | - | - | - | - | - | |
Total Revenue Allocation | - | - | - | - | - | - | |
Expenditures | |||||||
Salaries | 252,766 | 271,185 | 212,406 | 270,144 | 58,779 | 57,738 | |
Reimbursed Release Time | - | - | - | - | - | - | |
Total Salaries and Reimbursed Release Time | 252,766 | 271,185 | 212,406 | 270,144 | 58,779 | 57,738 | |
Operating Expenses | 65,327 | 80,449 | 25,653 | 51,261 | 54,796 | 25,608 | |
Total Expenditures (not including Benefits) | 318,093 | 351,634 | 238,058 | 321,405 | 113,576 | 83,346 | |
Benefits* | - | 94,214 | 94,214 | 93,852 | - | -362 | |
Total Expenditures and Benefits: | 318,093 | 445,848 | 332,272 | 415,257 | 113,576 | 82,985 | |
Results of Operations | |||||||
Transfers To | - | - | - | - | - | - | |
Transfers From | - | - | - | - | - | - | |
Total Funding Transfers To/(From) | - | - | - | - | - | - | |
Total Expenses and Funding Transfers | 318,093 | 445,848 | 332,272 | 415,257 | 113,576 | 82,985 |
*Benefits are budgeted centrally and then allocated throughout the year. The benefit amount reflected in the 16-17 Budget Column is a projected figure.